Construction progress update
Construction at La Luna has been moving along, despite COVID-19 which only saw a couple of small delays.
In general, the building program is proceeding very well, with projected completion end of 1st quarter next year, 2021.
The second-floor slab has been poured, with the formwork being installed for the top floor.
The final slab is due to be poured by June 30, and steelwork commencing in July.